Title: SUPPLEMENTAL REQUIREMENTS FOR
GENERAL MATERIAL DDG 51 ARLEIGH BURKE CLASS and DDG
1000 ZUMWALT CLASS |
Rev. S |
Date 3/20/07 |
|
|
|
|
||
|
SDRL CODE: E011,
WELDING, BRAZING AND ALLIED PROCESS PROCEDURE: Welding, brazing and allied processes
shall be in accordance with MIL-STD-278F.
One (1) Copy of procedures and qualification test data, as required by
MIL-STD-248, shall be submitted to the Buyer for review and approval in
accordance with the delivery schedule shown on the P.O. SDRL CODE: E012,
WELDING, BRAZING AND ALLIED PROCESS PROCEDURE: Welding, brazing and allied processes
shall be in accordance with ABS NVR Part 8, Chapter 3,
Sec. 3 (modified NAVSEA S9074-AR-GIB-010/278.
One (1) Copy of ABS approved procedures and qualification test data,
in accordance with ABS NVR Part 8, Chapter 3, Sec. 4 (modified NAVSEA
S9074-AQ-GIB-010/248), shall be submitted to the Buyer for review in
accordance with the delivery schedule shown on the P.O. Note: When submitting weld procedures
to ABS for approval, attach any previous Navy approvals as supporting
documentation (i.e., Navy approval Letter “Navy Signed”, Electric Boat VPAR,
etc). Applicable NDT procedures (VT, PT, MT,
RT, UT, etc.), written in accordance with ABS NVR Part 8, Chapter 3, Section
3 (modified NAVSEA S9074-AR-GIB-010/278) and sub-tier documents (NAVSEA
T9074-AS-GIB-010/271 and MIL-STD-2035A), shall be approved by the Vendor, NDT
Level III Inspector and submitted to the Buyer for review. |
|||