Bath Iron Works

                        

A GENERAL DYNAMICS COMPANY

                         Appendix G

Title:

SUPPLEMENTAL REQUIREMENTS FOR GENERAL MATERIAL

 

DDG 51 ARLEIGH BURKE CLASS and DDG 1000 ZUMWALT CLASS

 

Rev.

R

Date

9/18/07

 

APPENDIX G HOME

 

REVISION HISTORY

 

 

SDRL CODE:  E011, WELDING, BRAZING AND ALLIED PROCESS PROCEDURE:

 

        Welding, brazing and allied processes shall be in accordance with MIL-STD-278F.  One (1) Copy of procedures and qualification test data, as required by MIL-STD-248, shall be submitted to the Buyer for review and approval in accordance with the delivery schedule shown on the P.O.

 

 

SDRL CODE:  E012, WELDING, BRAZING AND ALLIED PROCESS PROCEDURE:

      

         Welding, brazing and allied processes shall be in accordance with ABS NVR Part 8, Chapter 3, Sec. 3 (modified NAVSEA S9074-AR-GIB-010/278.  One (1) Copy of ABS Surveyor approved procedures and qualification test data, in accordance with ABS NVR Part 8, Chapter 3, Sec. 4 (modified NAVSEA S9074-AQ-GIB-010/248), shall be submitted to the Buyer for review in accordance with the delivery schedule shown on the P.O.

           Note: When submitting weld procedures to the ABS Surveyor for approval, attach any previous Navy approvals as supporting documentation (i.e., Navy approval Letter, Electric Boat VPAR, etc.

      

       Applicable NDT procedures (VT, PT, MT, RT, UT, etc.), written in accordance with ABS NVR Part 8, Chapter 3, Section 3 (modified NAVSEA S9074-AR-GIB-010/278) and sub-tier documents (NAVSEA T9074-AS-GIB-010/271 and MIL-STD-2035A), shall be submitted to the Buyer for review and approval.